Undisclosed Client
Systematic review, testing and commissioning that took a newly built biogas plant safely through to final approval
A new biogas plant has been built on Lolland to convert organic material into green energy. Before the plant could go into operation, every section had to be checked, tested and fine-tuned. From the start of construction until the plant received final approval, Leap Solutions and the customer worked together to carry out the project.
Leap Solutions started with a line walk, reviewing the P&ID drawings against what had actually been installed. As a result, deviations were found and fixed early, before they could affect later phases.
We then carried out cold and hot testing of the plant, so both mechanical and process functions were tested under controlled conditions.
The plant was then commissioned one section at a time, and the operating parameters were fine-tuned in close collaboration with the customer.
From the first review to final approval, Leap Solutions was the technical partner that made sure the newly built plant had a structured and reliable path to stable operation.